Burnup chart

De Scrum Manager BoK
Esta página es una versión traducida de la página Gráfico de producto. La traducción está completa al 100 %.
⏱ 5 min  ·  📅 2026
The burnup chart is a planning tool used by the Product Owner that shows the expected progress of the project based on the team's velocity. Unlike the burndown chart, which measures what remains, the burnup chart measures what has been built and projects when the planned releases will be reached.

It is a living document that does not represent fixed plans but forecasts, which are updated after each sprint as the Product Backlog evolves and the team's actual velocity becomes better known.

When to use it

  • To tell the customer or stakeholders when each release of the product is likely to be ready.
  • When the product scope may change during development: the burnup chart visually shows how those changes affect the expected dates.
  • As an expectation management tool: the three forecast lines (pessimistic, realistic, and optimistic) honestly show the range of uncertainty.

How to build it

The chart uses a Cartesian diagram with:

  • Y axis (vertical): estimated effort in story points or another unit used by the team.
  • X axis (horizontal): time measured in sprints.


Burnup chart axes


Three velocity lines are drawn, based on the team's track record or on an initial estimate with a margin:

  • Optimistic: velocity in the best previous sprints (or initial estimate + positive margin).
  • Realistic: the team's average velocity.
  • Pessimistic: velocity in the worst previous sprints (or initial estimate - negative margin).

Each product version is placed on the vertical axis at the position corresponding to the total estimated effort required to build it. The points where that position intersects the three velocity lines project onto the horizontal axis the sprint in which it could be completed.

Example

Team conventions:

  • Unit of estimation: story points.
  • Fixed-length monthly sprints (20 working days).
  • 4-person team with an average velocity of 400 points per sprint.


4-person team with a velocity of 400 points per sprint
Burnup chart axes


Version 1.0 requires the first four stories, with an estimated effort of 950 points (150+250+250+300). It is placed at the value 950 on the vertical axis.

ID History Work Version and cumulative estimate
1History A 1.0150 Version 1.0
950 points
2Story B 1.0250
3History C 1.0250
4History D 1.0300
5History A 1.1250 Version 1.1
1700 points
6Story B 1.1350
7History E 1.0150
8History D 1.1500 Version 1.2
2550 points
9History C 1.1150
10History E 1.1200
11History F 1.0TBD Not estimated
12History A 1.2TBD
13Story B 1.2TBD
14History F 1.1TBD
The planned versions are placed on the vertical axis.
Product Backlog and planned versions


The points where it crosses the pessimistic, realistic, and optimistic velocity lines project the sprint in which version 1.0 could be completed in each scenario.

Common mistake

Using the burnup chart as a fixed plan. The burnup chart is not a promise: it is a forecast that changes with every sprint. Presenting it to stakeholders as a committed date rather than as a range of uncertainty creates false expectations and erodes trust when the forecasts change. The three lines (pessimistic, realistic, optimistic) exist precisely to communicate that uncertainty honestly.

Resources

📄 Scrum Master syllabusFree download · Scrum Manager

See also

Want to advance your Agile journey? You can look for upcoming courses and exams, or progress at your own pace by becoming a member of the Agile Club. This membership includes exclusive resources, e-learning classrooms, and access to Skill Arena—a space to practice and measure your Agile skills at your own speed.